File mdi_sheet1.txt -- Last modified Wed Sep 27 17:28:42 1995 COMMISSIONING PHASE BLOCK SHEET 1. INSTRUMENT AND BLOCK NUMBER: MDI, Block 1 2. BLOCK IDENTIFICATION: MDI Early Switch-on 3. PURPOSE: Start MDI CCD Bake-out for Cleanliness 4. SUB-BLOCKS: (see Note 1) NR. IDENTIFICATION 1.1 Switch on DEP & start CCD bake-out 1.2 Switch-on Filter Oven Heater 1.3 Thermal Adjustments 1.4 CCD Thermal Adjustment 1.5 End CCD Bake-out 5. SUB-BLOCKS TABLE: (see Note 2) NR. - DURATION - PREVIOUS - COMMANDING - TELEMETRY - POINTING 1.1 2:00 N/A PRO,NRT-d M None 1.2 1:30 Nom. PRO,NRT-d M None 1.3 0:20 Nom. NRT-d M None 1.4 0:20 Nom NRT-d M None 1.5 0:30 Nom. NRT-d M None 6. SCHEDULING REQUIREMENTS: (see Note 3) 1.1 about 12 hours after launch, as soon as M rate TM is available; if MDI is turned off for SSD1 or any other reason, then Block 1.1 must be repeated within a few hours after the interruption of power 1.2 about 1 to 3 days after 1.1; should be repeated promptly after any interruption of power to MDI 1.3 about 10 days after 1.1 1.4 about 14 days after 1.1 1.5 about 7 days after 1.4 7. SPECIAL REQUIREMENTS: (see Note 4) Coordination with FOT required 8. SUCCESS CRITERIA AND/OR EXPECTED OUTPUT: MDI in Sleep Mode, CCD, Optics Package and filter oven temperatures within limits. 9. RELEVANT PROCEDURES 1.1 TSTOL m_pconpri - switch on DEP TSTOL m_htron - switch on heater controllers TSTOL m_hopspt - set optics package heaters TSTOL m_ccdspt - set CCD heaters; start CCD bake-out 1.2 TSTOL m_ovenon - switch on prime oven controller TSTOL m_ovenspt 1.3 TSTOL m_hopspt - set optics package heaters 1.4 TSTOL m_ccdspt - set CCD heaters 10. CROSS-REFERENCE TO TEST SHEETS: (list identifiers for test sheets) TBS 11. RELEVANT SECTION OF TIMELINE (backpage) ; MDI Acronyms: ; DEP - Dedicated Experiment Processor; MDI internal control processor ; IP - Image Processor; MDI internal data processor ; ISS - Image Stabilization System ; OP - MDI Optics Package ; EP - MDI Electronics Package ; VC2 - Virtual Channel 2; MDI 160k telemetry delivered to EOF in realtime ; VC3 - Virtual Channel 3; MDI 160k telemetry recorded for delivery to SU ; ddd & hh:mm # Action # Comment BLOCK1 -- MDI EARLY SWITCH-ON COMMENT: These early switch-on activities are entirely internal and should have no interaction with other experiments. NOTE: MDI needs medium rate TM for switch-on. If not available, wait until established. (Medium rate TM planned for approximately 12 hours after launch) BLOCK1.1 -- START CCD BAKE-OUT 0 & 12:00 # Begin MDI Activation to SLEEP Mode # Duration 1 hour 0 & 12:05 # Establish power up configuration 0 & 12:15 # Switch on power converters and DEP 0 & 12:30 # Verify DEP functionality 0 & 13:00 # Switch on & verify adjustable CCD heater 0 & 13:10 # Set CCD heater to +30 deg C # 14 day bakeout 0 & 13:15 # Switch on & verify Optics Package heater 0 & 13:25 # Set OP heater to +30 deg C # 10 day bakeout 0 & 13:40 # Switch off S/C substitution heaters 0 & 14:00 # MDI in SLEEP Mode ; Verify that EP is not too cold and that both EP and OP are above ; nominal to increase outgassing. BLOCK1.2 -- SWITCH-ON FILTER OVEN HEATER 1 & 01:00 # Switch on & verify Filter Oven heater # MDI SLEEP Mode 1 & 01:10 # Set Filter Oven heater to +35 deg C 1 & 02:00 # Adjust settings for CCD and OP heaters