SOHO COMMISSIONING STATUS AT END OF EARLY EXPERIMENT COMMISSIONING PHASE END OF MISSION DAY 19 20 December 1995 EXPERIMENT -- BLOCKS COMPLETED -- STATUS -- COMMENT PLANNED -- ACTUAL GOLF -- 1,2 -- 1,2 -- On Hold -- On Target VIRGO -- 1 -- 1 -- Outgassing -- On Target MDI -- 1.1-1.4 -- 1.1-1.4 -- CCD Bake-out -- First Images 2.1-2.4 2.1-2.5 ahead of Schedule SUMER -- 1 -- 1,2.1 -- Outgassing -- Mechanisms Bake-out Exercised ahead of Schedule CDS -- 1 -- 1 -- Outgassing -- On Target LASCO/EIT -- 1 -- 1 -- CCD Bake-out -- On Target Outgassing UVCS -- 1 -- 1 -- Outgassing -- Some Mechanisms 2.1-2.3 2.1-2.3 Released ahead of Schedule SWAN -- 1,2 -- 1,3.1 -- Deep Sky -- Geocorona and Moon Survey Obs. (Block 2) postponed by PI CELIAS -- 1.1-1.13 -- 1.1-1.10 -- Bake-out -- Bake-out extended ERNE -- All -- All -- Nominal Obs. -- On Target COSTEP -- All -- All -- Nominal Obs. -- On Target Piet Martens, ESA SOC