File sumer_sheet1.txt -- Last modified Wed Nov 1 15:00:56 1995 COMMISSIONING PHASE BLOCK SHEET 1. INSTRUMENT AND BLOCK NUMBER: SUMER, Block 1 2. BLOCK IDENTIFICATION: SUMER Switch-on and Start Outgassing 3. PURPOSE: Intial checkout and start outgassing 4. SUB-BLOCKS: NR. IDENTIFICATION 1.1 Switch-on 1.2 Non-operational Heaters OFF 1.3 Initial Commissioning (without detector and deflector HV) 1.4 Switch ON Non-operational Heaters 1.5 Adjustment and Finetuning 1.6 Adjustment and Finetuning 5. SUB-BLOCKS TABLE: NR. - DURATION - PREVIOUS - COMMANDING - TELEMETRY - POINTING 1.1 0:10 N/A PRO M None 1.2 0:10 Nom PRO M None 1.3 4:10 Nom NRT-d H Nom 1.4 0:10 Nom PRO M None 1.5 (1) 1:00 Nom. NRT-d,PRO H Nom 1.6 (1) 1:30 Nom. NRT-d,PRO H Nom (1) May require switching On and OFF again of non-op heaters, witch requires FOT Procs 6. SCHEDULING REQUIREMENTS: A.s.a.p. after SVM initial check-out (planned for day 11, TBC) 1.1-1.4 on same day 1.5 one day after 1.4 1.6 one day after 1.5 7. SPECIAL REQUIREMENTS: Coordination with FOT required 8. SUCCESS CRITERIA AND/OR EXPECTED OUTPUT: SUMER HK OK, electronics on, door partially open, RSC image through window, detector A and detector B stimulation pulses. SUMER outgassing 9. RELEVANT PROCEDURES To be supplied 10. CROSS-REFERENCE TO TEST SHEETS: (list identifiers for test sheets) To be supplied