File uvcs_sheet2.txt -- Last modified Mon Aug 28 13:06:21 1995 COMMISSIONING PHASE BLOCK SHEET 1. INSTRUMENT AND BLOCK NUMBER: UVCS, Block 2 2. BLOCK IDENTIFICATION: UVCS Outgassing 3. PURPOSE: Prepare for optimal outgassing, and outgas 4. SUB-BLOCKS: (see Note 1) NR. IDENTIFICATION 2.1 Prepare outgassing, partially open door 2.2 Adjust Heaters 2.3 Adjust Heaters 2.4 Complete outgassing, re-adjust heaters 5. SUB-BLOCKS TABLE: (see Note 2) NR. - DURATION - PREVIOUS - COMMANDING - TELEMETRY - POINTING 2.1 1:30 Nom. NRT-d H None 2.2 0:15 Nom. NRT-d H None 2.3 (1)0:15 Nom. NRT-d H None 2.4 0:30 Nom. NRT-d H None (1) To be repeated daily from 2.2 to 2.4 6. SCHEDULING REQUIREMENTS: (see Note 3) 2.2 preferably in same contact time, about 5:00 hours later than 2.1 2.4 3 weeks after 2.2 (23 days with some flexibility: 20-27 days) 2.3 to be repeated daily between 2.2 and 2.4. Outgassing may be interrupted by SVM operations such as MCC2; in that case close door (0:30) and re-open afterwards (0:30). No adjustments with door closed. 7. SPECIAL REQUIREMENTS: (see Note 4) None 8. SUCCESS CRITERIA AND/OR EXPECTED OUTPUT: UVCS completely outgassed, HK normal. 9. RELEVANT PROCEDURES None (?) 10. CROSS-REFERENCE TO TEST SHEETS: (list identifiers for test sheets) 11. RELEVANT SECTION OF TIMELINE BLOCK2 -- UVCS OUTGASSING ; Outgassing period (takes about 3 weeks) BLOCK2.1 -- START OUTGASSING - PARTIALLY OPEN DOOR 12 & 10:00 # Both (TBD) LYA/OVI detectors ON # (HV OFF); 1:00, NRT-d ; # For better outgassing. Monitor XDLs temperature 12 & 11:00 # Partially open door # UVCS already in diagn. mode; 0:30, NRT-d BLOCK2.2 -- ADJUST HEATERS 12 & 18:50 # Adjust htr. setpoints # to further increase temp.; 0:15, NRT-d ; Note: During the outgassing period, the MOM and Grating heaters should always ; ---- be on in order to prevent condensation of contaminats on the optics. 12 & 19:00 # Monitor temperatures # If necessary, adjust heaters; NRT-s 12 & 19:05 # Start outgassing period # 3 weeks; NRT-s ; From day 13 to day 17 the heaters may need to be adjusted on a contingency base 13 & 18:50 # Adjust htr. setpoints # to further increase temp.; 0:15, NRT-d 13 & 19:00 # Monitor temperatures # If necessary, adjust heaters; NRT-s 14 & 18:50 # Adjust htr. setpoints # to further increase temp.; 0:15, NRT-d 14 & 19:00 # Monitor temperatures # If necessary, adjust heaters; NRT-s 15 & 18:50 # Adjust htr. setpoints # to further increase temp.; 0:15, NRT-d 15 & 19:00 # Monitor temperatures # If necessary, adjust heaters; NRT-s 16 & 18:50 # Adjust htr. setpoints # to further increase temp.; 0:15, NRT-d 16 & 19:00 # Monitor temperatures # If necessary, adjust heaters; NRT-s 17 & 18:50 # Adjust htr. setpoints # to further increase temp.; 0:15, NRT-d 17 & 19:00 # Monitor temperatures # If necessary, adjust heaters; NRT-s BLOCK2.3 -- INTERRUPT OUTGASSING - CLOSE DOOR 18 & 17:10 # Both LYA/OVI detectors OFF (TBD) # 0:10, NRT-d 18 & 17:30 # Close door # 0:20, NRT-d 19 & 00:00 # Start no P/L operations # S/C MCC2 BLOCK2.4 -- PARTIALLY OPEN DOOR - COMPLETE OUTGASSING 20 & 00:00 # End no P/L operations # S/C MCC2 21 & 09:00 # Both (TBD) LYA/OVI detectors ON # (HV OFF); 0:10, NRT-d ; # For better outgassing. Monitor XDLs temperature 21 & 09:10 # Partially open door # 0:20, NRT-d ; From day 22 to day 35, it would be desirable to have 15-min NRT-d every ; day, in order to be able to adjust the heaters on a contingency base 35 & 00:00 # End outgassing period # adjust htrs to nominal level