File virgo_sheet1.txt -- Last modified Fri Aug 18 14:54:34 1995 COMMISSIONING PHASE BLOCK SHEET 1. INSTRUMENT AND BLOCK NUMBER: VIRGO, Block 1 2. BLOCK IDENTIFICATION: VIRGO Early Switch-on 3. PURPOSE: Early switch-on to protect SPM and enhance outgassing 4. SUB-BLOCKS: (see Note 1) NR. IDENTIFICATION 1.1 Switch-on, receive daily pulse 1.2 Continue switch-on 5. SUB-BLOCKS TABLE: (see Note 2) NR. - DURATION - PREVIOUS - COMMANDING - TELEMETRY - POINTING 1.1 1:00 N/A PROC M None 1.2 2:00 Nom.+(1) PROC M None (1) Receive daily pulse previously at 0:00 6. SCHEDULING REQUIREMENTS: (see Note 3) 1.2 one day after 1,1, with daily pulse (at 24:00 UT) in between 7. SPECIAL REQUIREMENTS: (see Note 4) Requires coordination with FOT Daily pulse received before 1.2 to be executed 8. SUCCESS CRITERIA AND/OR EXPECTED OUTPUT: VIRGO switched-on and cover released, HK normal 9. RELEVANT PROCEDURES PROC1, 6, 7, 8, 9, 10, 11, 18 10. CROSS-REFERENCE TO TEST SHEETS: (list identifiers for test sheets) N/A (done with the FOT Procedures) 11. RELEVANT SECTION OF TIMELINE (backpage) ; ; ; ***** edited 22 February 1995 for the SOWG Meeting, GSFC 23/24-Feb-1995 ; ***** re-edited as input for the cruise phase planning 10 March 1995 ; ***** new version with Blocks etc. 2 June 1995 ; Time-line has the required format: TIME # ACTION # COMMENT ; Time has the format: ddd & hh:mm:ss, or ddd, or ddd & hh, or ddd & hh:mm ; ***** times are given in UTC: 14:00-22:00 corresonds to GSFC working hours ; ***** that is the 8h contact time ; PROCx: are TSTOL procedures described in: ; SOHO/VIRGO FOT PROCEDURES, VIR-PMO-DAT/G-111, issue 2.2, 25 May 1995 ; (some update is needed, the updated version will be available by ; 9 June 1995: change PROC 19 and 20; define PROC22, 23, 24) BLOCK1 -- VIRGO EARLY SWITCH-ON BLOCK1.1 -- SWITCH-ON, RECEIVE DAILY PULSE 4 & 21:00 # PROC1: Power on, load day of mission; enable ; start-up with daily pulse; 4 & 21:20 # PROC6: SPM-A switch on and heaters on; 4 & 21:40 # PROC7: SPM-B switch on and heaters on; 4 & 22:00 # End VIRGO-FOT activities ; at 5 & 00:00 (24h pulse of S/C) the experiment ; will be synchronized with the daily pulse ; BLOCK1.2 -- CONTINUE SWITCH-ON 5 & 14:00 # PROC8: PMO-B switch on 5 & 14:30 # PROC9: PMO-A switch on 5 & 14:25 # PROC10: LOI switch on 5 & 14:50 # PROC11: DIARAD switch on 5 & 15:05 # PROC18: Cover release (for nominal it takes 25 min ; for redundant +20 min), test with short opening ; of PMO-A cover 5 & 15:50 # End VIRGO FOT activities ; ; outgassing of VIRGO instruments with cover closed until after MCC2; ; instruments are running and electrically tested; in principle ; no commanding needed (only if something unexpected happens) ; ; NOTES: Note 1: Sub-blocks are functional units within a block. Operations can be interrupted between blocks, but usually not within a block. Note 2: In this table the following information is sought: DURATION: Estimation of time needed (dd & hh:mm), without contingency. PREVIOUS: Previous (sub)block(s) necessarily completed before the present subblock. Nominal (entry: Nom) is all (sub)blocks with lower number. Exceptions are noted with X (i.e. X 2.5, 2.6 means, all previous subblocks need be completed, except 2.5 and 2.6) TELEMETRY: Telemetry mode and submode required. Options: High (H), Medium (M), Low (L). For submodes: 1,2,3 (??). Nominal during cruise phase is H2 after ?? days, M between 12 hours and ?? days, and L before 12 hours after launch. COMMANDING: Commanding mode required. Options are NRT dedicated (entry NRT-d), NRT shared (NRT-s), STOL procedure (entry: PRO and procedure identifyer), no commanding, for example monitoring HK, or outgassing (entry: None). Others ?? POINTING: Pointing requirements: none (entry: None), or nominal to Sun with no accuray guaranteed during cruise (entry: Nom). Other options are: no interference by other instruments or reaction wheels (No-I), and ?? SCHEDULING: Any scheduling requirements, such as at a certain time after launch, before or after MCC2, Please leave entries blank only when the information is not known, not for nominal (entry: Nom), or not applicable (N/A), or obvious cases (they may not be obvious to others). Please use footnotes to the table if entry does not fit into table. Note 3: Describe any scheduling requirements, for example preferred, earliest and latest time for early switch-on activities, scheduling before or after MCC2, preferred time or preferred interval with respect to previous activities (for example intervals between intercalibrations), etc.?? Note 4: Describe any special circumstances, for example when an activity is to be continued during non-contact hours, under automatic control, when coordination with other experiments or the FOT (for SVM operations) is required, etc.