File virgo_sheet2.txt -- Last modified Mon Aug 14 11:03:08 1995 COMMISSIONING PHASE BLOCK SHEET 1. INSTRUMENT AND BLOCK NUMBER: VIRGO, Block 2 2. BLOCK IDENTIFICATION: VIRGO Functional Commissioning 3. PURPOSE: First Sun on Radiometers 4. SUB-BLOCKS: (see Note 1) NR. IDENTIFICATION 2.1 Open Covers, Test CROM 2.2 Initialize LOI, SPM-A 5. SUB-BLOCKS TABLE: (see Note 2) NR. - DURATION - PREVIOUS - COMMANDING - TELEMETRY - POINTING 2.1 3:50 Nom. PROC H Nom. 2.2 1:00 Nom. PROC H Nom. 6. SCHEDULING REQUIREMENTS: (see Note 3) 2.1 a.s.a.p. after MCC2 2.2 approx. one week after 2.1 (5-10 days, but not before day 30) 7. SPECIAL REQUIREMENTS: (see Note 4) Note: after completion of this block VIRGO will perform daily time-tagged telecommanding for normal operations, to be performed by FOT. This will not affect ECS scheduling. (see comments in timeline). Coordination with FOT required. 8. SUCCESS CRITERIA AND/OR EXPECTED OUTPUT: VIRGO functioning verified, ready for calibration 9. RELEVANT PROCEDURES PROC17, PROC19, PROC20 10. CROSS-REFERENCE TO TEST SHEETS: (list identifiers for test sheets) N/A (done with the FOT Procedures) 11. RELEVANT SECTION OF TIMELINE (backpage) BLOCK2 -- VIRGO FUNCTIONAL COMMISSIONING NOTE: BLOCK2 involves test of redundant operation, check with Froehlich BLOCK2.1 -- OPEN COVERS, TEST CROM 23 & 14:00 # PROC20: Open covers and test DIARAD, PMOA & B, put them ; in operational mode from here on; ; open covers and test SPM A & B, close covers again; 23 & 16:45 # PROC17: LOI commissioning 2nd part: ; open cover and test LOI, close cover again 23 & 22:00 # End of VIRGO FOT activities until day 30 ; ; From here on we will have daily time tagged telecommanding during ; the non contact times; the list with the daily commands will ; be prepared by VIRGO with the DSN contact times (received on Friday ; for the following next week). The file will be sent to the FOT 24h ; before the uploading time. ; ; at the 24h pulse between days xx/xx+1 VIRGO will be re-synchronized ; by programmed time tagged command) together with GOLF. This will be ; after GOLF has tested the redundant sensor and decided which one ; they will use (after day 50) ; ((((((((((((((((helioseismology sychronization)))))))))))))))) BLOCK2.2 -- INITIALIZE LOI, SPM-A ; 30 & 14:00 # PROC19: LOI, SPM-A in operational mode 30 & 15:00 # End of VIRGO FOT activities