SOHO Daily Meeting Minutes for Wednesday, 28 March 2001
ANNOUNCEMENTS
-------------
* Network GITT security scan testing is going on today from
14:30-16:30 UT.
* Friday - Building 3: PMI contractors are scheduled to perform
preventive maintenance on building 3-UPS-20 on March 30 from 9AM until
4:30PM. The UPS unit will be in bypass mode and the load will be on
commercial power during this activity. No impact to operations is
expected. 3-UPS-20 supports the SOHO, ACE, W/P and XTE missions.
* Due to the Canberra strikes, all commanding should be done before
Canberra passes start each evening. If there are any impacts to
the instruments from these strikes, please tell the SOCs.
* Due to DSS27 and then Canberra passes tomorrow, commanding for large
loads should be done between 15:30 and 17:50 UT.
FOT REPORT
----------
Spacecraft Status: Nominal
Spacecraft Anomalies: None
Accomplished Activities: VIRGO, RSL
Planned Activities: VIRGO, CELIAS
Upcoming Operations: None
Ground Anomalies: None
SOLAR STATUS
------------
03/26 DOY 085 - 03/27 DOY 086
EIT daily On-Line Solar Status and observations:
http://umbra.nascom.nasa.gov/eit/plan/log_form20010328.html
LASCO daily On-Line Solar Status and observations:
http://lasco-www.nrl.navy.mil/observations/2001/obs20010328.html
AR Transient Events target: AR 9393
---------------------------
INSTRUMENT STATUS
-----------------
CDS: Nominal. Map of active region belts.
SUMER: Nominal. Refspecs off the northwest limb.
UVCS: Nominal. Coronal hole observations in the southwest and synoptic.
LASCO: Nominal. C2 and C3 synoptics.
EIT: Nominal. Half resolution 195 Angstrom CME watch and synoptics.
MDI: Nominal. Cropped full disk magnetograms and dopplergrams in
best focus for continuous contact.
TRACE: Nominal. The day begins with a central meridian scan in 171;
we then resume tracking AR 9393. Have switched to wide (8' x 4')
FOV for UV, at a slight cost to the cadence; EUV remains at
full-frame (8' x 8').