Early Operations

P.Martens gave a report on early operations timelining (see annex 17). Early operations now includes the cruise phase (120days), the commissioning phase (S/C + P/L; 30days), and the initial science operations (30days). There is an action on the PI's (12.1) to comment and update the early operations timeline plan. Input to P.Martens before July 31 (preferably in electronic form).



Bernhard Fleck